WFMAC Transmission – West Fort McMurray 500 kV Line

See All Projects
Project Details

Location: Northcentral Alberta

Client: Valard

Project

The West Fort McMurray (WFMAC) 500 kV Transmission Line Project includes over 310 miles of high voltage transmission line, expansion of the existing Livock substation, and construction of the new Thickwood Hills substation, all located in Northcentral Alberta.  The project is expected to be in-service by mid-2019.

Geotechnical Profiling and Foundation Design

QS conducted a desktop study of two proposed alignments.  This included collection and review of available project and public information along the alignments; geo-referencing of over 50 geologic maps; and reports on the surface and subsurface geology, hydrogeology, and geomorphology.  18 expected soil profiles were developed, and primary and secondary foundation types were selected for approximately 2,600 structures between the two alignments.  Bid level designs for multiple soil profiles and foundation types were subsequently developed for pricing.

Following route selection, a limited geotechnical investigation was completed.  Results from this and the indicative pricing were used to refine soil profiles to 17.  IFC foundation design packages were developed through 30%, 60% and 90% stages with Owner and contractor reviews.  Final designs included drilled shafts, driven piles, helical piles & anchors, and grouted anchors.

Geotechnical Investigation

QS managed a comprehensive geotechnical investigation program, completing borings at each of the 1,392 structure locations.  Between two and five geotechnical drills operated simultaneously to remain ahead of construction, averaging around two borings per day per rig.  Specific challenges included drilling in extreme cold, in environmentally sensitive areas, and during ice breakup.  The resulting data was used to select the optimal foundation type for each structure.

Construction

Helical pile anchors were the primary foundation type, supporting 1,182 guyed structures.  QS was responsible for onsite geotechnical confirmation, quality assurance and compliance reporting.  13 work fronts operated simultaneously at times, with up to 7 driven pile, 6 helical pile, 1 drilled shaft, 1 pre-drill, and 1 anchor testing crew running concurrently.

The revised 17 soil profiles proved highly accurate, with approximately just 2% of structure locations encountering unexpected geotechnical materials.  QS developed an additional 4 general soil profiles to mitigate this, as well as a handful of site-specific foundation designs.

Highlights

  • Over 310 miles of new, 500 kV high voltage transmission line
  • Preliminary geotechnical profiling to develop bid level designs
  • Geotechnical borings at 1,392 structure locations to optimize foundation selection